The project Schulcampus Frankfurt Westend is based on an innovative and sustainable construction concept.

Timber-concrete composite (HBV) meets DELTABEAM®. Peikko designed the slab system for the demanding building project using a timber-concrete composite structure. The Swiss company ERNE AG Holzbau produced the prefabricated wood-composite components in its own factory and combined them with DELTABEAM® composite beams to form an efficient slim-floor structure.

The building will have 3 levels, approx. 122 m long and approx. 30 m wide. The reinforced concrete work was executed by Grossmann, all other structural work on the construction site was conducted by ERNE Holzbau.

The design as a composite structure with DELTABEAM® slim floors allows very high load capacities with low construction height.

Читать далее down-arrow.png

Факты проекта

Размер проекта:
16 600 m2
Этажи проекта:
3
Разработчик:
Stadtschulamt Frankfurt a.M.
Строительная компания:
ERNE AG HOLZBAU & Grossmann
Строительный дизайнер:
MWV Bauingenieure AG
Архитектор:
gmp International GmbH
Год завершения:
2019